26INR0074 · Solar · Wilson County
Anila Solar
Anila Solar is a 201 MW solar project in Wilson County, Texas, connecting at Tap 345kV 5133 Elm Creek - 5901 San Miguel Gen Ckt 1. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 09/30/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 26INR0074
- Capacity
- 201 MW
- Fuel
- Solar (PV)
- County
- Wilson County
- Interconnecting entity
- Alina Energy LLC
- Projected COD
- 09/30/2028
- Entered queue
- 01/20/2023
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 03/06/2025FIS Approved → IA Signed
- 07/10/2024FIS Requested → FIS Approved
- 01/20/2023Entered the queue with 201 MW, projected COD 09/30/2028
- 01/20/2023Screening → FIS Requested
Other projects at this substation
No other projects at this substation.