26INR0073 · BESS · Karnes County
Charro Creek Storage 3 SLF
Charro Creek Storage 3 SLF is a 0 MW battery storage project in Karnes County, Texas, connecting at Tap 345kV 5725 PAWNEESW5 - 8164 COLETO7A. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/31/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 26INR0073
- Capacity
- 0 MW
- Fuel
- BESS (BA)
- Substation
- Tap 345kV 5725 PAWNEESW5 - 8164 COLETO7A
- County
- Karnes County
- Interconnecting entity
- Charro Creek Solar LLC
- Projected COD
- 12/31/2029
- Entered queue
- 01/30/2023
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 02/10/2023Screening → FIS Requested
- 01/30/2023Entered the queue with 0 MW, projected COD 12/31/2029
Other projects at this substation
| Charro Creek Solar 1 SLF | Solar | 203 MW | FIS Requested |
| Charro Creek Storage 1 SLF | BESS | 0 MW | FIS Requested |
| Charro Creek Solar 2 SLF | Solar | 203 MW | FIS Requested |
| Charro Creek Storage 2 SLF | BESS | 0 MW | FIS Requested |