25INR0656 · BESS · Wise County
Gilleys Energy Storage
Gilleys Energy Storage is a 306 MW battery storage project in Wise County, Texas, connecting at Tap 345 kV 1730 West Krum - 6111 Riley CKT 2. ERCOT's October 2026 report shows it at the FIS Approved stage with a projected commercial operation date of 04/21/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 25INR0656
- Capacity
- 306 MW
- Fuel
- BESS (BA)
- County
- Wise County
- Interconnecting entity
- Gilleys Energy Storage, LLC
- Projected COD
- 04/21/2028
- Entered queue
- 05/06/2024
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 01/05/2026FIS Requested → FIS Approved
- 05/06/2024Entered the queue with 306 MW, projected COD 04/21/2028
- 05/06/2024Screening → FIS Requested
Other projects at this substation