ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
25INR0554 · BESS · Brazoria County

Dan Kearney BESS

COD delayed 1×

Dan Kearney BESS is a 204 MW battery storage project in Brazoria County, Texas, connecting at 39703 TNFM524 138kV. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 02/28/2029. Its projected COD has been pushed back 1 time in the reports compared.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
25INR0554
Capacity
204 MW
Fuel
BESS (BA)
Interconnecting entity
Dan Kearney BESS LLC
Projected COD
02/28/2029
Entered queue
01/03/2024
ERCOT zone
COASTAL
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/01/2026
    Projected COD moved 10/01/2027 → 02/28/2029 (+17 months)
  • 09/18/2026
    FIS Requested → FIS Approved
  • 10/18/2024
    FIS Approved → IA Signed
  • 01/03/2024
    Entered the queue with 204 MW, projected COD 10/01/2027
  • 01/03/2024
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.