25INR0550 · BESS · Brazoria County
Friendswood Energy Storage
COD delayed 1×
Friendswood Energy Storage is a 105 MW battery storage project in Brazoria County, Texas, connecting at TAP 138kV 39010 HASTINGS - 38980 FRIENDSWOOD. ERCOT's October 2026 report shows it at the FIS Approved stage with a projected commercial operation date of 03/30/2028. Its projected COD has been pushed back 1 time in the reports compared.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 25INR0550
- Capacity
- 105 MW
- Fuel
- BESS (BA)
- County
- Brazoria County
- Interconnecting entity
- Friendswood Energy Storage LLC
- Projected COD
- 03/30/2028
- Entered queue
- 01/17/2024
- ERCOT zone
- COASTAL
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/01/2026Projected COD moved 09/30/2027 → 03/30/2028 (+6 months)
- 12/11/2025FIS Requested → FIS Approved
- 01/17/2024Entered the queue with 105 MW, projected COD 09/30/2027
- 01/17/2024Screening → FIS Requested