LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
25INR0504 · Solar · Franklin County

Lazy Frog Solar SLF

Lazy Frog Solar SLF is a 100 MW solar project in Franklin County, Texas, connecting at 11688 Thorn Tree Switch 345kV. ERCOT's October 2026 report shows it at the FIS Approved stage with a projected commercial operation date of 04/17/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
25INR0504
Capacity
100 MW
Fuel
Solar (PV)
Interconnecting entity
Lazy Frog Solar, LLC
Projected COD
04/17/2028
Entered queue
09/22/2023
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/28/2025
    FIS Requested → FIS Approved
  • 05/10/2024
    Screening → FIS Requested
  • 09/22/2023
    Entered the queue with 100 MW, projected COD 04/17/2028

Other projects at this substation

Lazy Frog Storage SLFBESS0 MWFIS Approved