25INR0494 · Wind · Brazoria County
Willow Beach Wind
Willow Beach Wind is a 202 MW wind project in Brazoria County, Texas, connecting at Tap 138 kV Bus# 42100 HUD_8 – Bus# 42960 MUSTNG_S04_8 138kV CKT# 4. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 10/01/2027.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 25INR0494
- Capacity
- 202 MW
- Fuel
- Wind (WT)
- County
- Brazoria County
- Interconnecting entity
- Capital Wind, LLC
- Projected COD
- 10/01/2027
- Entered queue
- 09/20/2023
- ERCOT zone
- COASTAL
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 06/16/2025FIS Approved → IA Signed
- 11/18/2024FIS Requested → FIS Approved
- 09/20/2023Entered the queue with 202 MW, projected COD 10/01/2027
- 09/20/2023Screening → FIS Requested
Other projects at this substation
No other projects at this substation.