ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
25INR0473 · BESS · Jones County

Crowded Star I BESS

Crowded Star I BESS is a 203 MW battery storage project in Jones County, Texas, connecting at 68014 Open Sky. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 07/09/2027.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
25INR0473
Capacity
203 MW
Fuel
BESS (BA)
Substation
68014 Open Sky
Interconnecting entity
Jones City Solar II, LLC
Projected COD
07/09/2027
Entered queue
08/09/2023
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 12/01/2025
    FIS Approved → IA Signed
  • 11/10/2025
    FIS Requested → FIS Approved
  • 08/09/2023
    Entered the queue with 203 MW, projected COD 07/09/2027
  • 08/09/2023
    Screening → FIS Requested