Crowded Star I BESS is a 203 MW battery storage project in Jones County, Texas, connecting at 68014 Open Sky. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 07/09/2027.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 25INR0473
- Capacity
- 203 MW
- Fuel
- BESS (BA)
- Substation
- 68014 Open Sky
- County
- Jones County
- Interconnecting entity
- Jones City Solar II, LLC
- Projected COD
- 07/09/2027
- Entered queue
- 08/09/2023
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 12/01/2025FIS Approved → IA Signed
- 11/10/2025FIS Requested → FIS Approved
- 08/09/2023Entered the queue with 203 MW, projected COD 07/09/2027
- 08/09/2023Screening → FIS Requested