ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
25INR0434 · BESS · Harris County

Bluegill BESS

COD delayed 1×

Bluegill BESS is a 251 MW battery storage project in Harris County, Texas, connecting at Tap 138 kV 40130 Atascocita - 40690 East Gate. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 10/31/2028. Its projected COD has been pushed back 1 time in the reports compared.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
25INR0434
Capacity
251 MW
Fuel
BESS (BA)
Interconnecting entity
Bluegill BESS, LLC
Projected COD
10/31/2028
Entered queue
05/18/2023
ERCOT zone
HOUSTON
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/01/2026
    Projected COD moved 10/31/2027 → 10/31/2028 (+12 months)
  • 05/18/2023
    Entered the queue with 251 MW, projected COD 10/31/2027
  • 05/18/2023
    Screening → FIS Requested