25INR0434 · BESS · Harris County
Bluegill BESS
COD delayed 1×
Bluegill BESS is a 251 MW battery storage project in Harris County, Texas, connecting at Tap 138 kV 40130 Atascocita - 40690 East Gate. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 10/31/2028. Its projected COD has been pushed back 1 time in the reports compared.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 25INR0434
- Capacity
- 251 MW
- Fuel
- BESS (BA)
- County
- Harris County
- Interconnecting entity
- Bluegill BESS, LLC
- Projected COD
- 10/31/2028
- Entered queue
- 05/18/2023
- ERCOT zone
- HOUSTON
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/01/2026Projected COD moved 10/31/2027 → 10/31/2028 (+12 months)
- 05/18/2023Entered the queue with 251 MW, projected COD 10/31/2027
- 05/18/2023Screening → FIS Requested
Other projects at this substation