LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
25INR0405 · BESS · Matagorda County

Pledgor BESS

Pledgor BESS is a 100 MW battery storage project in Matagorda County, Texas, connecting at Tap Gulftie (43340) – Pledger (43120) circuit 60. ERCOT's October 2026 report shows it at the FIS Approved stage with a projected commercial operation date of 04/06/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
25INR0405
Capacity
100 MW
Fuel
BESS (BA)
Interconnecting entity
Pledgor BESS
Projected COD
04/06/2028
Entered queue
04/25/2023
ERCOT zone
COASTAL
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 08/27/2024
    FIS Requested → FIS Approved
  • 04/25/2023
    Entered the queue with 100 MW, projected COD 04/06/2028
  • 04/25/2023
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.