LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
25INR0389 · BESS · Milam County

Stoneridge BESS

Stoneridge BESS is a 102 MW battery storage project in Milam County, Texas, connecting at Tap 345 kV 13429 SANDOW SWITCH - 7040 AUSTROP CKT 2. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 12/31/2026.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
25INR0389
Capacity
102 MW
Fuel
BESS (BA)
Interconnecting entity
Stoneridge Solar, LLC
Projected COD
12/31/2026
Entered queue
03/09/2023
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 07/10/2025
    Energization Approved → Sync Approved
  • 06/26/2025
    IA Signed → Energization Approved
  • 09/06/2024
    FIS Requested → FIS Approved
  • 04/19/2024
    FIS Approved → IA Signed
  • 03/09/2023
    Entered the queue with 102 MW, projected COD 12/31/2026
  • 03/09/2023
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.