ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
25INR0347 · BESS · Brazos County

Cadet Storage

Cadet Storage is a 104 MW battery storage project in Brazos County, Texas, connecting at Tap 69kV 32864 BRYN_ATK69 to 32873 BRYN SHADY. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 07/28/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
25INR0347
Capacity
104 MW
Fuel
BESS (BA)
Interconnecting entity
TX BESS 5, LLC
Projected COD
07/28/2029
Entered queue
04/24/2023
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 04/24/2023
    Entered the queue with 104 MW, projected COD 07/28/2029
  • 04/24/2023
    Screening → FIS Requested