25INR0337 · Solar · Bell County
Butcherbird Solar
Butcherbird Solar is a 116 MW solar project in Bell County, Texas, connecting at Tap 138 kV - Bell County #133 to Bartlett Switch #114. ERCOT's October 2026 report shows it at the FIS Approved stage with a projected commercial operation date of 01/31/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 25INR0337
- Capacity
- 116 MW
- Fuel
- Solar (PV)
- County
- Bell County
- Interconnecting entity
- Butcherbird Solar, LLC
- Projected COD
- 01/31/2029
- Entered queue
- 12/06/2023
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 12/02/2025FIS Requested → FIS Approved
- 12/06/2023Entered the queue with 116 MW, projected COD 01/31/2029
- 12/06/2023Screening → FIS Requested
Other projects at this substation