25INR0330 · Solar · Brazoria County
Clutch City Solar Phase II
Clutch City Solar Phase II is a 251 MW solar project in Brazoria County, Texas, connecting at tap 138kV 42960 Mustang Bayou – 42100 Hudson CKT #04. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 07/01/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 25INR0330
- Capacity
- 251 MW
- Fuel
- Solar (PV)
- County
- Brazoria County
- Interconnecting entity
- HZ SOLAR I, LLC
- Projected COD
- 07/01/2028
- Entered queue
- 02/10/2023
- ERCOT zone
- COASTAL
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 02/11/2025FIS Requested → IA Signed
- 02/10/2023Entered the queue with 251 MW, projected COD 07/01/2028
- 02/10/2023Screening → FIS Requested
Other projects at this substation
| Clutch City Solar Phase I | Solar | 201 MW | IA Signed |