25INR0311 · BESS · Falls County
RIVERBEND STORAGE SLF
RIVERBEND STORAGE SLF is a 0 MW battery storage project in Falls County, Texas, connecting at TAP 345 KV LINE FROM TRADINGHOUSE (#3405) TO TEMPLE PECAN CREEK (#3412) SUBSTATIONS. ERCOT's October 2026 report shows it at the FIS Approved stage with a projected commercial operation date of 12/31/2027.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 25INR0311
- Capacity
- 0 MW
- Fuel
- BESS (BA)
- County
- Falls County
- Interconnecting entity
- Riverbend Renewables, LLC
- Projected COD
- 12/31/2027
- Entered queue
- 03/03/2023
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 07/23/2024FIS Requested → FIS Approved
- 03/03/2023Entered the queue with 0 MW, projected COD 12/31/2027
- 03/03/2023Screening → FIS Requested
Other projects at this substation
| RIVERBEND SOLAR SLF | Solar | 302 MW | FIS Requested |