25INR0293 · BESS · Wharton County

TOCE BESS 1

COD delayed 1×

TOCE BESS 1 is a 205 MW battery storage project in Wharton County, Texas, connecting at 138 kV Danevang Switching Station (Bus# 5546). ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 12/31/2028. Its projected COD has been pushed back 1 time in the reports compared.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
25INR0293
Capacity
205 MW
Fuel
BESS (BA)
Interconnecting entity
TOCE BESS 1, LLC
Projected COD
12/31/2028
Entered queue
09/22/2023
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/01/2026
    Projected COD moved 05/31/2028 → 12/31/2028 (+7 months)
  • 12/30/2024
    FIS Approved → IA Signed
  • 11/07/2024
    FIS Requested → FIS Approved
  • 09/22/2023
    Entered the queue with 205 MW, projected COD 05/31/2028
  • 09/22/2023
    Screening → FIS Requested