ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
25INR0286 · Solar · Madison County

Savannah Oaks Solar

Savannah Oaks Solar is a 201 MW solar project in Madison County, Texas, connecting at Tap 345kV 46020 Limestone Plant - 967 Gibbons Creek. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 09/30/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
25INR0286
Capacity
201 MW
Fuel
Solar (PV)
Interconnecting entity
Savannah Oaks Solar Project LLC
Projected COD
09/30/2028
Entered queue
12/02/2022
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 12/02/2022
    Entered the queue with 201 MW, projected COD 09/30/2028
  • 12/02/2022
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.