25INR0286 · Solar · Madison County
Savannah Oaks Solar
Savannah Oaks Solar is a 201 MW solar project in Madison County, Texas, connecting at Tap 345kV 46020 Limestone Plant - 967 Gibbons Creek. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 09/30/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 25INR0286
- Capacity
- 201 MW
- Fuel
- Solar (PV)
- County
- Madison County
- Interconnecting entity
- Savannah Oaks Solar Project LLC
- Projected COD
- 09/30/2028
- Entered queue
- 12/02/2022
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 12/02/2022Entered the queue with 201 MW, projected COD 09/30/2028
- 12/02/2022Screening → FIS Requested
Other projects at this substation
No other projects at this substation.