25INR0262 · BESS · Galveston County
Shepard Energy Storage
Shepard Energy Storage is a 257 MW battery storage project in Galveston County, Texas, connecting at # 38900 Hidden Lakes - # 42015 PHR 138 KV. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 06/30/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 25INR0262
- Capacity
- 257 MW
- Fuel
- BESS (BA)
- County
- Galveston County
- Interconnecting entity
- Shepard Energy Storage LLC
- Projected COD
- 06/30/2028
- Entered queue
- 12/09/2022
- ERCOT zone
- HOUSTON
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 03/19/2026FIS Requested → FIS Approved
- 01/17/2024FIS Approved → IA Signed
- 12/09/2022Entered the queue with 257 MW, projected COD 06/30/2028
- 12/09/2022Screening → FIS Requested
Other projects at this substation