LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
25INR0262 · BESS · Galveston County

Shepard Energy Storage

Shepard Energy Storage is a 257 MW battery storage project in Galveston County, Texas, connecting at # 38900 Hidden Lakes - # 42015 PHR 138 KV. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 06/30/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
25INR0262
Capacity
257 MW
Fuel
BESS (BA)
Interconnecting entity
Shepard Energy Storage LLC
Projected COD
06/30/2028
Entered queue
12/09/2022
ERCOT zone
HOUSTON
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 03/19/2026
    FIS Requested → FIS Approved
  • 01/17/2024
    FIS Approved → IA Signed
  • 12/09/2022
    Entered the queue with 257 MW, projected COD 06/30/2028
  • 12/09/2022
    Screening → FIS Requested

Other projects at this substation