25INR0232 · Solar · Matagorda County
Isaac Solar
Isaac Solar is a 51 MW solar project in Matagorda County, Texas, connecting at 8114 Conoco 138kV. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 04/15/2027.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 25INR0232
- Capacity
- 51 MW
- Fuel
- Solar (PV)
- Substation
- 8114 Conoco 138kV
- County
- Matagorda County
- Interconnecting entity
- Industrial Bravo Project LLC
- Projected COD
- 04/15/2027
- Entered queue
- 10/27/2022
- ERCOT zone
- COASTAL
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 12/18/2025FIS Requested → FIS Approved
- 10/18/2023FIS Approved → IA Signed
- 10/27/2022Entered the queue with 51 MW, projected COD 04/15/2027
- 10/27/2022Screening → FIS Requested
Other projects at this substation
No other projects at this substation.