25INR0220 · Solar · Navarro County
Hector Solar
Hector Solar is a 82 MW solar project in Navarro County, Texas, connecting at Haney (213) - Hubbard_8 (3515) 138kV Line. ERCOT's October 2026 report shows it at the Screening stage with a projected commercial operation date of 10/08/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 25INR0220
- Capacity
- 82 MW
- Fuel
- Solar (PV)
- County
- Navarro County
- Interconnecting entity
- Hector Solar, LLC
- Projected COD
- 10/08/2028
- Entered queue
- 10/24/2022
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/24/2022Entered the queue with 82 MW, projected COD 10/08/2028
Other projects at this substation
| Hector Storage | BESS | 43 MW | FIS Requested |