25INR0220 · Solar · Navarro County

Hector Solar

Hector Solar is a 82 MW solar project in Navarro County, Texas, connecting at Haney (213) - Hubbard_8 (3515) 138kV Line. ERCOT's October 2026 report shows it at the Screening stage with a projected commercial operation date of 10/08/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
25INR0220
Capacity
82 MW
Fuel
Solar (PV)
Interconnecting entity
Hector Solar, LLC
Projected COD
10/08/2028
Entered queue
10/24/2022
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/24/2022
    Entered the queue with 82 MW, projected COD 10/08/2028