ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
25INR0202 · BESS · Kerr County

East West BESS

East West BESS is a 123 MW battery storage project in Kerr County, Texas, connecting at 7750 LCRA MOUNTAIN HOME SUB. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 03/17/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
25INR0202
Capacity
123 MW
Fuel
BESS (BA)
Interconnecting entity
East West Energy Storage, LLC
Projected COD
03/17/2028
Entered queue
09/27/2022
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 07/12/2024
    FIS Requested → IA Signed
  • 09/27/2022
    Entered the queue with 123 MW, projected COD 03/17/2028
  • 09/27/2022
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.