25INR0193 · Solar · Gonzales County
Nockenut Springs Solar 4
Nockenut Springs Solar 4 is a 201 MW solar project in Gonzales County, Texas, connecting at The 345 kV Elm Creek - South Texas Project Line (Bus #5133 - #5915). ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 06/05/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 25INR0193
- Capacity
- 201 MW
- Fuel
- Solar (PV)
- County
- Gonzales County
- Interconnecting entity
- Pecan Springs Energy, LLC
- Projected COD
- 06/05/2029
- Entered queue
- 08/31/2022
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 08/31/2022Entered the queue with 201 MW, projected COD 06/05/2029
- 08/31/2022Screening → FIS Requested
Other projects at this substation
No other projects at this substation.