25INR0189 · BESS · Fayette County
Staccato BESS
Staccato BESS is a 202 MW battery storage project in Fayette County, Texas, connecting at 138kV WARDA #7312.. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 05/28/2027.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 25INR0189
- Capacity
- 202 MW
- Fuel
- BESS (BA)
- Substation
- 138kV WARDA #7312.
- County
- Fayette County
- Interconnecting entity
- Staccato Storage, LLC
- Projected COD
- 05/28/2027
- Entered queue
- 11/07/2022
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 03/11/2026FIS Requested → FIS Approved
- 08/27/2024FIS Approved → IA Signed
- 12/15/2022Screening → FIS Requested
- 11/07/2022Entered the queue with 202 MW, projected COD 05/28/2027