LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
25INR0171 · BESS · Brazoria County

Pinewood BESS

Withdrawn

Pinewood BESS is a 101 MW battery storage project in Brazoria County, Texas, with no point of interconnection listed. It is no longer active in ERCOT's interconnection queue.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
25INR0171
Capacity
101 MW
Fuel
BESS
Substation
Not listed
Interconnecting entity
Not listed
Projected COD
n/a
Entered queue
08/20/2025
ERCOT zone
n/a
Size category
n/a

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 08/20/2025
    Listed as inactive

Other projects at this substation

No other projects at this substation.