25INR0170 · Solar · Brazoria County

Pinewood Solar

Pinewood Solar is a 151 MW solar project in Brazoria County, Texas, connecting at 43020 Seabreeze 345kV. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 02/29/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
25INR0170
Capacity
151 MW
Fuel
Solar (PV)
Interconnecting entity
Brazoria Solar II, LLC
Projected COD
02/29/2028
Entered queue
09/02/2022
ERCOT zone
COASTAL
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 05/08/2025
    FIS Requested → IA Signed
  • 06/20/2023
    Screening → FIS Requested
  • 09/02/2022
    Entered the queue with 151 MW, projected COD 02/29/2028

Other projects at this substation

No other projects at this substation.