25INR0166 · Solar · Hill County
Compadre Solar II
COD delayed 1×
Compadre Solar II is a 201 MW solar project in Hill County, Texas, connecting at Tap 345kV 68090 Sam Switch – 3389 Fort Smith. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 12/31/2026. Its projected COD has been pushed back 1 time in the reports compared.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 25INR0166
- Capacity
- 201 MW
- Fuel
- Solar (PV)
- County
- Hill County
- Interconnecting entity
- Hill Solar II, LLC
- Projected COD
- 12/31/2026
- Entered queue
- 09/15/2022
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/01/2026Projected COD moved 10/01/2026 → 12/31/2026 (+3 months)
- 07/16/2026Energization Approved → Sync Approved
- 04/27/2026IA Signed → Energization Approved
- 06/16/2025FIS Requested → FIS Approved
- 12/24/2024FIS Approved → IA Signed
- 03/07/2023Screening → FIS Requested
- 09/15/2022Entered the queue with 201 MW, projected COD 10/01/2026
Other projects at this substation