25INR0142 · BESS · Glasscock County
Sagewood BESS
Sagewood BESS is a 101 MW battery storage project in Glasscock County, Texas, connecting at tap McDonald Road Switch (1333) – Pastores Switch (10121) ckt 1. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 03/31/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 25INR0142
- Capacity
- 101 MW
- Fuel
- BESS (BA)
- County
- Glasscock County
- Interconnecting entity
- Sagewood BESS, LLC
- Projected COD
- 03/31/2028
- Entered queue
- 09/21/2022
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 12/29/2022Screening → FIS Requested
- 09/21/2022Entered the queue with 101 MW, projected COD 03/31/2028