25INR0140 · BESS · Ector County

Seragio BESS

Seragio BESS is a 201 MW battery storage project in Ector County, Texas, connecting at 11140 ECTRCNTYN_8 138kV. ERCOT's October 2026 report shows it at the FIS Approved stage with a projected commercial operation date of 04/30/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
25INR0140
Capacity
201 MW
Fuel
BESS (BA)
Interconnecting entity
Seragio BESS, LLC
Projected COD
04/30/2028
Entered queue
09/15/2022
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 04/14/2026
    FIS Requested → FIS Approved
  • 12/29/2022
    Screening → FIS Requested
  • 09/15/2022
    Entered the queue with 201 MW, projected COD 04/30/2028