25INR0138 · BESS · Glasscock County
Champaign BESS
Champaign BESS is a 201 MW battery storage project in Glasscock County, Texas, connecting at Tap 138kV Shaw POD (18664) – Desert Wind Sub (11283). ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 03/31/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 25INR0138
- Capacity
- 201 MW
- Fuel
- BESS (BA)
- County
- Glasscock County
- Interconnecting entity
- Champaign BESS, LLC
- Projected COD
- 03/31/2028
- Entered queue
- 09/21/2022
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 07/31/2025FIS Approved → IA Signed
- 08/13/2024FIS Requested → FIS Approved
- 12/29/2022Screening → FIS Requested
- 09/21/2022Entered the queue with 201 MW, projected COD 03/31/2028