25INR0103 · BESS · Brazoria County
Elio BESS
COD delayed 1×
Elio BESS is a 205 MW battery storage project in Brazoria County, Texas, connecting at 138 kV Weinbrenner Station (Bus #42990). ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 12/31/2028. Its projected COD has been pushed back 1 time in the reports compared.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 25INR0103
- Capacity
- 205 MW
- Fuel
- BESS (BA)
- Substation
- 138 kV Weinbrenner Station (Bus #42990)
- County
- Brazoria County
- Interconnecting entity
- Elio Energy LLC
- Projected COD
- 12/31/2028
- Entered queue
- 07/05/2022
- ERCOT zone
- COASTAL
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/01/2026Projected COD moved 08/05/2028 → 12/31/2028 (+5 months)
- 10/01/2026Capacity 317 → 205 MW
- 10/31/2024FIS Requested → FIS Approved
- 09/15/2024FIS Approved → IA Signed
- 05/15/2023Screening → FIS Requested
- 07/05/2022Entered the queue with 317 MW, projected COD 08/05/2028
Other projects at this substation
No other projects at this substation.