25INR0101 · BESS · Collin County
Drake BESS
Drake BESS is a 257 MW battery storage project in Collin County, Texas, connecting at #833 Wylie Switch 138kV. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 01/29/2027.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 25INR0101
- Capacity
- 257 MW
- Fuel
- BESS (BA)
- Substation
- #833 Wylie Switch 138kV
- County
- Collin County
- Interconnecting entity
- Mallard Energy Storage LLC
- Projected COD
- 01/29/2027
- Entered queue
- 06/02/2022
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 06/18/2025FIS Requested → FIS Approved
- 05/06/2025FIS Approved → IA Signed
- 06/17/2022Screening → FIS Requested
- 06/02/2022Entered the queue with 257 MW, projected COD 01/29/2027
Other projects at this substation
No other projects at this substation.