25INR0097 · Solar · Clay County
Soleil Solar
Soleil Solar is a 452 MW solar project in Clay County, Texas, connecting at Tap 345 kV 1730 Krum West Switch - 6111 Riley ckt 2. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 12/28/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 25INR0097
- Capacity
- 452 MW
- Fuel
- Solar (PV)
- County
- Clay County
- Interconnecting entity
- Soleil Solar, LLC
- Projected COD
- 12/28/2028
- Entered queue
- 08/26/2022
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 05/09/2025FIS Requested → IA Signed
- 08/26/2022Entered the queue with 452 MW, projected COD 12/28/2028
- 08/26/2022Screening → FIS Requested