25INR0061 · BESS · Bee County

Argenta Storage

Argenta Storage is a 192 MW battery storage project in Bee County, Texas, connecting at Tap 345kV 8689 Tango - 8606 Goddard. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 06/30/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
25INR0061
Capacity
192 MW
Fuel
BESS (BA)
Interconnecting entity
Charter Oak Storage, LLC
Projected COD
06/30/2028
Entered queue
06/27/2022
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 04/05/2024
    FIS Requested → IA Signed
  • 07/13/2022
    Screening → FIS Requested
  • 06/27/2022
    Entered the queue with 192 MW, projected COD 06/30/2028

Other projects at this substation

Argenta SolarSolar310 MWIA Signed