24INR0605 · Gas · Wharton County
TEXAS GULF SULPHUR REPOWER
TEXAS GULF SULPHUR REPOWER is a 16 MW natural gas project in Wharton County, Texas, connecting at 43340 Gulftie 138 kV. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 03/27/2025.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 24INR0605
- Capacity
- 16 MW
- Fuel
- Gas (GT)
- Substation
- 43340 Gulftie 138 kV
- County
- Wharton County
- Interconnecting entity
- Wharton County Generation, LLC
- Projected COD
- 03/27/2025
- Entered queue
- 03/01/2022
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 02/17/2025IA Signed → Sync Approved
- 02/01/2024FIS Requested → FIS Approved
- 07/27/2023Screening → FIS Requested
- 03/01/2022Entered the queue with 16 MW, projected COD 03/27/2025
- 03/01/2022FIS Approved → IA Signed
Other projects at this substation
No other projects at this substation.