24INR0530 · BESS · Brazoria County
Southside Energy
Southside Energy is a 101 MW battery storage project in Brazoria County, Texas, connecting at Tap 138kV 42960 Mustang Bayou - 42100 HUDSON ckt 4. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/31/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 24INR0530
- Capacity
- 101 MW
- Fuel
- BESS (BA)
- County
- Brazoria County
- Interconnecting entity
- Southside Energy, LLC
- Projected COD
- 12/31/2028
- Entered queue
- 02/27/2023
- ERCOT zone
- COASTAL
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/24/2023Screening → FIS Requested
- 02/27/2023Entered the queue with 101 MW, projected COD 12/31/2028