LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
24INR0530 · BESS · Brazoria County

Southside Energy

Southside Energy is a 101 MW battery storage project in Brazoria County, Texas, connecting at Tap 138kV 42960 Mustang Bayou - 42100 HUDSON ckt 4. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/31/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
24INR0530
Capacity
101 MW
Fuel
BESS (BA)
Interconnecting entity
Southside Energy, LLC
Projected COD
12/31/2028
Entered queue
02/27/2023
ERCOT zone
COASTAL
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/24/2023
    Screening → FIS Requested
  • 02/27/2023
    Entered the queue with 101 MW, projected COD 12/31/2028

Other projects at this substation

No other projects at this substation.