24INR0505 · Wind · Zapata County

Corralitos Wind 1

Corralitos Wind 1 is a 196 MW wind project in Zapata County, Texas, connecting at Tap 345kV 80225 CENIZO7C - 80307 DELSOL7C (New ETT Tiempo Substation). ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 12/01/2027.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
24INR0505
Capacity
196 MW
Fuel
Wind (WT)
Interconnecting entity
Vaquero Wind Energy, LLC
Projected COD
12/01/2027
Entered queue
01/19/2023
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 06/19/2025
    FIS Requested → IA Signed
  • 01/19/2023
    Entered the queue with 196 MW, projected COD 12/01/2027
  • 01/19/2023
    Screening → FIS Requested

Other projects at this substation

Corralitos Wind 2Wind195 MWIA Signed