24INR0500 · BESS · Harris County

Claire BESS

Claire BESS is a 406 MW battery storage project in Harris County, Texas, connecting at 40011 Cedar Bayou 138kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/17/2027.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
24INR0500
Capacity
406 MW
Fuel
BESS (BA)
Interconnecting entity
BRP Blue Topaz 3, LLC
Projected COD
12/17/2027
Entered queue
01/30/2023
ERCOT zone
HOUSTON
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 01/30/2023
    Entered the queue with 406 MW, projected COD 12/17/2027
  • 01/30/2023
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.