24INR0494 · BESS · Lampasas County
Hana Springs BESS
Hana Springs BESS is a 101 MW battery storage project in Lampasas County, Texas, connecting at 7064 LAMPASAS 138KV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 05/15/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 24INR0494
- Capacity
- 101 MW
- Fuel
- BESS (BA)
- Substation
- 7064 LAMPASAS 138KV
- County
- Lampasas County
- Interconnecting entity
- Black Mountain Energy Storage II LLC
- Projected COD
- 05/15/2028
- Entered queue
- 11/18/2022
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 11/18/2022Entered the queue with 101 MW, projected COD 05/15/2028
- 11/18/2022Screening → FIS Requested