24INR0493 · BESS · Fort Bend County
Crowned Heron BESS 2
Crowned Heron BESS 2 is a 154 MW battery storage project in Fort Bend County, Texas, connecting at WA Parish 345 kV Bus #44000. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 10/02/2026.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 24INR0493
- Capacity
- 154 MW
- Fuel
- BESS (BA)
- Substation
- WA Parish 345 kV Bus #44000
- County
- Fort Bend County
- Interconnecting entity
- RWE Renewables
- Projected COD
- 10/02/2026
- Entered queue
- 11/15/2022
- ERCOT zone
- HOUSTON
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 04/06/2026Energization Approved → Sync Approved
- 01/27/2026IA Signed → Energization Approved
- 08/20/2024FIS Approved → IA Signed
- 01/28/2024FIS Requested → FIS Approved
- 11/15/2022Entered the queue with 154 MW, projected COD 10/02/2026
- 11/15/2022Screening → FIS Requested
Other projects at this substation
| Crowned Heron BESS | BESS | 154 MW | Sync Approved |