24INR0481 · BESS · Harris County
Little York BESS
COD delayed 1×
Little York BESS is a 10 MW battery storage project in Harris County, Texas, connecting at Station Name (TDSP Station Code): Little York (LK). ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 11/12/2026. Its projected COD has been pushed back 1 time in the reports compared.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 24INR0481
- Capacity
- 10 MW
- Fuel
- BESS (BA)
- County
- Harris County
- Interconnecting entity
- ESTX-PLD-HOUSTON5, LLC
- Projected COD
- 11/12/2026
- Entered queue
- 08/20/2025
- ERCOT zone
- HOUSTON
- Size category
- Small
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/01/2026Projected COD moved 07/27/2026 → 11/12/2026 (+4 months)
- 06/15/2026Energization Approved → Sync Approved
- 06/05/2026IA Signed → Energization Approved
- 08/20/2025Entered the queue with 10 MW, projected COD 07/27/2026
- 08/20/2025Screening → IA Signed
Other projects at this substation
No other projects at this substation.