LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
24INR0440 · Solar · Gonzales County

Starling Solar

Starling Solar is a 145 MW solar project in Gonzales County, Texas, connecting at 138-kV Birdhouse (7255). ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 01/28/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
24INR0440
Capacity
145 MW
Fuel
Solar (PV)
Interconnecting entity
Starling Solar, LLC
Projected COD
01/28/2028
Entered queue
10/06/2022
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 02/17/2026
    FIS Requested → IA Signed
  • 06/16/2023
    Screening → FIS Requested
  • 10/06/2022
    Entered the queue with 145 MW, projected COD 01/28/2028

Other projects at this substation

No other projects at this substation.