24INR0407 · Solar · Hill County

Mercury Solar III

Mercury Solar III is a 204 MW solar project in Hill County, Texas, connecting at 68092 Liberty Station 345kV. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 04/01/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
24INR0407
Capacity
204 MW
Fuel
Solar (PV)
Interconnecting entity
Mercury Solar
Projected COD
04/01/2029
Entered queue
08/03/2022
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 12/12/2025
    FIS Requested → IA Signed
  • 08/03/2022
    Entered the queue with 204 MW, projected COD 04/01/2029
  • 08/03/2022
    Screening → FIS Requested

Other projects at this substation

Mercury Storage SLFBESS0 MWFIS Requested