24INR0399 · Solar · Motley County
Buzios Solar
Buzios Solar is a 252 MW solar project in Motley County, Texas, connecting at Tap between Cottonwood (#59904) and White River (#23922). ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 07/31/2026.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 24INR0399
- Capacity
- 252 MW
- Fuel
- Solar (PV)
- County
- Motley County
- Interconnecting entity
- Roaring Springs Solar, LLC
- Projected COD
- 07/31/2026
- Entered queue
- 08/04/2022
- ERCOT zone
- PANHANDLE
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/01/2025Energization Approved → Sync Approved
- 08/27/2025IA Signed → Energization Approved
- 03/10/2025FIS Requested → FIS Approved
- 11/06/2023FIS Approved → IA Signed
- 08/04/2022Entered the queue with 252 MW, projected COD 07/31/2026
- 08/04/2022Screening → FIS Requested