24INR0376 · BESS · Wilson County
Huisache BESS
Huisache BESS is a 101 MW battery storage project in Wilson County, Texas, connecting at Tapping the Elm Creek to Shaula circuit 1. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 06/30/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 24INR0376
- Capacity
- 101 MW
- Fuel
- BESS (BA)
- County
- Wilson County
- Interconnecting entity
- Huisache Solar, LLC
- Projected COD
- 06/30/2029
- Entered queue
- 08/05/2022
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 08/12/2025FIS Requested → IA Signed
- 11/07/2022Screening → FIS Requested
- 08/05/2022Entered the queue with 101 MW, projected COD 06/30/2029
Other projects at this substation
| Huisache Solar | Solar | 126 MW | IA Signed |