24INR0274 · BESS · Collin County
Bufflehead BESS
Bufflehead BESS is a 154 MW battery storage project in Collin County, Texas, connecting at 2475 Lavon Switch 138kV. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 02/15/2027.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 24INR0274
- Capacity
- 154 MW
- Fuel
- BESS (BA)
- Substation
- 2475 Lavon Switch 138kV
- County
- Collin County
- Interconnecting entity
- Boxcar Energy Storage, LLC
- Projected COD
- 02/15/2027
- Entered queue
- 02/28/2022
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 02/27/2026FIS Requested → FIS Approved
- 04/10/2024FIS Approved → IA Signed
- 02/28/2022Entered the queue with 154 MW, projected COD 02/15/2027
- 02/28/2022Screening → FIS Requested