ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
24INR0208 · Solar · Milam County

Eastbell Milam Solar II

COD delayed 1×

Eastbell Milam Solar II is a 151 MW solar project in Milam County, Texas, connecting at 345 kV Bell County East Switch (bus# 3687) - TNP One (bus# 39950) circuit 2. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 11/01/2026. Its projected COD has been pushed back 1 time in the reports compared.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
24INR0208
Capacity
151 MW
Fuel
Solar (PV)
Interconnecting entity
Cattlemen Solar Park II LLC
Projected COD
11/01/2026
Entered queue
02/03/2022
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/01/2026
    Projected COD moved 07/15/2026 → 11/01/2026 (+4 months)
  • 11/20/2024
    Energization Approved → Sync Approved
  • 09/13/2024
    IA Signed → Energization Approved
  • 02/01/2024
    FIS Requested → FIS Approved
  • 10/25/2023
    FIS Approved → IA Signed
  • 02/03/2022
    Entered the queue with 151 MW, projected COD 07/15/2026
  • 02/03/2022
    Screening → FIS Requested

Other projects at this substation

Eastbell Milam SolarSolar245 MWSync Approved