24INR0201 · Solar · Wichita County
Short Creek Solar
Short Creek Solar is a 628 MW solar project in Wichita County, Texas, connecting at Tap 345kV 6101 Riley - 1425 Fisher Road Switch Ckt 1. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 12/17/2027.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 24INR0201
- Capacity
- 628 MW
- Fuel
- Solar (PV)
- County
- Wichita County
- Interconnecting entity
- Wichita Solar I, LLC
- Projected COD
- 12/17/2027
- Entered queue
- 01/20/2022
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 09/09/2026FIS Requested → FIS Approved
- 10/02/2024FIS Approved → IA Signed
- 10/12/2022Screening → FIS Requested
- 01/20/2022Entered the queue with 628 MW, projected COD 12/17/2027
Other projects at this substation
| Short Creek BESS | BESS | 156 MW | FIS Requested |