24INR0200 · Solar · Deaf Smith County
White Tail Solar
COD delayed 1×
White Tail Solar is a 227 MW solar project in Deaf Smith County, Texas, connecting at Tap 345kV Windmill (23910) – AJ Swope (23906). ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/29/2028. Its projected COD has been pushed back 1 time in the reports compared.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 24INR0200
- Capacity
- 227 MW
- Fuel
- Solar (PV)
- County
- Deaf Smith County
- Interconnecting entity
- Mule Deer Solar LLC
- Projected COD
- 12/29/2028
- Entered queue
- 02/07/2022
- ERCOT zone
- PANHANDLE
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/01/2026Projected COD moved 09/21/2027 → 12/29/2028 (+15 months)
- 10/21/2022Screening → FIS Requested
- 02/07/2022Entered the queue with 227 MW, projected COD 09/21/2027
Other projects at this substation
No other projects at this substation.