24INR0200 · Solar · Deaf Smith County

White Tail Solar

COD delayed 1×

White Tail Solar is a 227 MW solar project in Deaf Smith County, Texas, connecting at Tap 345kV Windmill (23910) – AJ Swope (23906). ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/29/2028. Its projected COD has been pushed back 1 time in the reports compared.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
24INR0200
Capacity
227 MW
Fuel
Solar (PV)
Interconnecting entity
Mule Deer Solar LLC
Projected COD
12/29/2028
Entered queue
02/07/2022
ERCOT zone
PANHANDLE
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/01/2026
    Projected COD moved 09/21/2027 → 12/29/2028 (+15 months)
  • 10/21/2022
    Screening → FIS Requested
  • 02/07/2022
    Entered the queue with 227 MW, projected COD 09/21/2027

Other projects at this substation

No other projects at this substation.