24INR0184 · Solar · Zapata County

Slate Solar Project

COD delayed 1×

Slate Solar Project is a 105 MW solar project in Zapata County, Texas, connecting at Tap 138kV 8646 Rio Bravo - 8985 San Ygancio. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 01/15/2030. Its projected COD has been pushed back 1 time in the reports compared.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
24INR0184
Capacity
105 MW
Fuel
Solar (PV)
Interconnecting entity
Ignis TX Solar Three LLC
Projected COD
01/15/2030
Entered queue
12/20/2021
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/01/2026
    Projected COD moved 10/30/2027 → 01/15/2030 (+27 months)
  • 07/13/2022
    Screening → FIS Requested
  • 12/20/2021
    Entered the queue with 105 MW, projected COD 10/30/2027

Other projects at this substation