24INR0167 · Solar · Wharton County
OCI SunRoper
OCI SunRoper is a 265 MW solar project in Wharton County, Texas, connecting at tap138kV #43190 South Lane City to #42985 Dyann CKT#60. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 10/01/2027.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 24INR0167
- Capacity
- 265 MW
- Fuel
- Solar (PV)
- County
- Wharton County
- Interconnecting entity
- OCI SunRoper LLC
- Projected COD
- 10/01/2027
- Entered queue
- 11/23/2021
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 04/17/2026FIS Requested → FIS Approved
- 07/10/2025FIS Approved → IA Signed
- 11/23/2021Entered the queue with 265 MW, projected COD 10/01/2027
- 11/23/2021Screening → FIS Requested
Other projects at this substation
No other projects at this substation.